Allegheny Power 2015 Annual Report Download - page 69

Download and view the complete annual report

Please find page 69 of the 2015 Allegheny Power annual report below. You can navigate through the pages in the report by either clicking on the pages listed below, or by using the keyword search tool below to find specific information within the annual report.

Page out of 163

  • 1
  • 2
  • 3
  • 4
  • 5
  • 6
  • 7
  • 8
  • 9
  • 10
  • 11
  • 12
  • 13
  • 14
  • 15
  • 16
  • 17
  • 18
  • 19
  • 20
  • 21
  • 22
  • 23
  • 24
  • 25
  • 26
  • 27
  • 28
  • 29
  • 30
  • 31
  • 32
  • 33
  • 34
  • 35
  • 36
  • 37
  • 38
  • 39
  • 40
  • 41
  • 42
  • 43
  • 44
  • 45
  • 46
  • 47
  • 48
  • 49
  • 50
  • 51
  • 52
  • 53
  • 54
  • 55
  • 56
  • 57
  • 58
  • 59
  • 60
  • 61
  • 62
  • 63
  • 64
  • 65
  • 66
  • 67
  • 68
  • 69
  • 70
  • 71
  • 72
  • 73
  • 74
  • 75
  • 76
  • 77
  • 78
  • 79
  • 80
  • 81
  • 82
  • 83
  • 84
  • 85
  • 86
  • 87
  • 88
  • 89
  • 90
  • 91
  • 92
  • 93
  • 94
  • 95
  • 96
  • 97
  • 98
  • 99
  • 100
  • 101
  • 102
  • 103
  • 104
  • 105
  • 106
  • 107
  • 108
  • 109
  • 110
  • 111
  • 112
  • 113
  • 114
  • 115
  • 116
  • 117
  • 118
  • 119
  • 120
  • 121
  • 122
  • 123
  • 124
  • 125
  • 126
  • 127
  • 128
  • 129
  • 130
  • 131
  • 132
  • 133
  • 134
  • 135
  • 136
  • 137
  • 138
  • 139
  • 140
  • 141
  • 142
  • 143
  • 144
  • 145
  • 146
  • 147
  • 148
  • 149
  • 150
  • 151
  • 152
  • 153
  • 154
  • 155
  • 156
  • 157
  • 158
  • 159
  • 160
  • 161
  • 162
  • 163

52
20162017 20172018 20182019*
Legacy
Obligation
Capacity
Performance
Legacy
Obligation
Capacity
Performance
Base
Generation
Capacity
Performance
(MW) ($/MWD) (MW) ($/MWD) (MW) ($/MWD) (MW) ($/MWD) (MW) ($/MWD) (MW) ($/MWD)
ATSI2,765 $114.234,210 $134.00375 $120.006,245 $151.50 — $149.986,245 $164.77
RTO875 $59.37 3,675 $134.00 985 $120.00 3,565 $151.50 240 $149.98 3,930 $164.77
AllOther
Zones
135 $119.13 $134.00 150 $120.00 — $151.50 35 ** 20 **
3,775 7,885 1,510 9,810 275 10,195
*Approximately885MWsremainuncommittedforthe2018/2019deliveryyear.
**Base Generation: 10 MWs cleared at $200.21/MWD and 25 MWs cleared at $149.98/MWD. Capacity Performance: 5 MWs cleared at
$215.00/MWDand15MWsclearedat$164.77/MWD.
PJMMarketReform:FERCOrderNo.745DR
OnMay23,2014,adividedthreejudgepaneloftheU.S.CourtofAppealsfortheD.C.CircuitissuedanopinionvacatingFERC
Order No. 745, which required that, under certain parameters, DR participating in organized wholesale energy markets be
compensatedatLMP.ThemajorityconcludedthatDRisaretailservice,andthereforefallsunderstate,andnotfederal,jurisdiction,
andthatFERC,therefore,lacksjurisdictiontoregulateDR.ThemajorityalsofoundthatevenifFERChadjurisdictionoverDR,Order
No.745wouldbearbitraryandcapriciousbecause,underitsrequirements,DRwasinappropriatelyreceivingadoublepayment(LMP
plusthesavingsofforegoneenergypurchases).OnJanuary25,2016,theUnitedStatesSupremeCourtreversedtheopinionofthe
U.S.CourtofAppealsfortheD.C.Circuitandremandedforfurtheraction,findingFERChasstatutoryauthorityundertheFPAto
regulatecompensationofdemandresponseresourcesinFERCjurisdictionalwholesalepowermarkets.TheUnitedStatesSupreme
CourtalsoreversedtheholdingthatFERC'sOrderNo.745wasarbitraryandcapricious,findingthattheorderincludeddetailed
supportofthechosencompensationmethod.
OnMay23,2014,asamendedSeptember22,2014,FESC,onbehalfofitsaffiliateswithmarketbasedrateauthorization,fileda
complaintaskingFERCtoissueanorderrequiringtheremovalofallportionsofthePJMTariffallowingorrequiringDRtobeincluded
inthePJMcapacitymarket,witharefundeffectivedateofMay23,2014.FESCalsorequestedthattheresultsoftheMay2014PJM
BRAbeconsideredvoidandlegallyinvalidtotheextentthatDRclearedthatauctionbecausetheparticipationofDRinthatauction
wasunlawful.However,inlightoftheUnitedStatesSupremeCourt'sJanuary25,2016decisiondiscussedabove,onJanuary29,
2016,FESCwithdrewthecomplaint.
ENVIRONMENTALMATTERS
Variousfederal,stateandlocalauthoritiesregulateFirstEnergywithregardtoairandwaterqualityandotherenvironmentalmatters.
CompliancewithenvironmentalregulationscouldhaveamaterialadverseeffectonFirstEnergy'searningsandcompetitivepositionto
theextentthatFirstEnergycompeteswithcompaniesthatarenotsubjecttosuchregulationsand,therefore,donotbeartheriskof
costsassociatedwithcompliance,orfailuretocomply,withsuchregulations.
CleanAirAct
FirstEnergycomplieswithSO2andNOxemissionreductionrequirementsundertheCAAandSIP(s)byburninglowersulfurfuel,
utilizingcombustioncontrolsandpostcombustioncontrols,generatingmoreelectricityfromlowerornonemittingplantsand/orusing
emissionallowances.
CSAPRrequiresreductionsofNOxandSO2emissionsintwophases(2015and2017),ultimatelycappingSO2emissionsinaffected
statesto2.4milliontonsannuallyandNOxemissionsto1.2milliontonsannually.CSAPRallowstradingofNOxandSO2emission
allowancesbetweenpowerplantslocatedinthesamestateandinterstatetradingofNOxandSO2emissionallowanceswithsome
restrictions.TheU.S.CourtofAppealsfortheD.C.CircuitorderedtheEPAonJuly28,2015,toreconsidertheCSAPRcapsonNOx
andSO2emissionsfrompowerplantsin13states,includingOhio,PennsylvaniaandWestVirginia.Thisfollowsthe2014U.S.
SupremeCourtrulinggenerallyupholdingEPA’sregulatoryapproachunderCSAPR,butquestioningwhetherEPArequiredupwind
statestoreduceemissionsbymorethantheircontributiontoairpollutionindownwindstates.EPAproposedaCSAPRupdateruleon
November16,2015,thatwouldreducesummertimeNOxemissionsfrompowerplantsin23statesintheeasternU.S.,including
Ohio,PennsylvaniaandWestVirginia,beginningin2017.DependingonhowtheEPAandthestatesimplementCSAPR,thefuture
costofcompliancemaybesubstantialandchangestoFirstEnergy'sandFES'operationsmayresult.
EPAtightenedtheprimaryandsecondaryNAAQSforozonefromthe2008standardlevelsof75PPBto70PPBonOctober1,2015.
EPAstatedthevastmajorityofU.S.countieswillmeetthenew70PPBstandardby2025duetootherfederalandstaterulesand
programsbutEPAwilldesignatethosecountiesthatfailtoattainthenew2015ozoneNAAQSbyOctober1,2017.Stateswillthen
haveroughlythreeyearstodevelopimplementationplanstoattainthenew2015ozoneNAAQS.DependingonhowtheEPAandthe
statesimplementthenew2015ozoneNAAQS,thefuturecostofcompliancemaybesubstantialandchangestoFirstEnergy’sand
FES’operationsmayresult.
53
MATSimposesemissionlimitsformercury,PM,andHClforallexistingandnewfossilfuelfiredelectricgeneratingunitseffectivein
April2015withaveragingofemissionsfrommultipleunitslocatedatasingleplant.UndertheCAA,statepermittingauthoritiescan
grantanadditionalcomplianceyearthroughApril2016,asneeded,includinginstanceswhennecessarytomaintainreliabilitywhere
electricgeneratingunitsarebeingclosed.OnDecember28,2012,theWVDEPgrantedaconditionalextensionthroughApril16,
2016forMATScomplianceattheFortMartin,HarrisonandPleasantsplants.OnMarch20,2013,thePADEPgrantedanextension
throughApril16,2016forMATScomplianceattheHatfield'sFerryandBruceMansfieldplants.OnFebruary5,2015,theOEPA
grantedanextensionthroughApril16,2016forMATScomplianceattheBayShoreandSammisplants.Nearlyallspendingfor
MATScomplianceatBayShoreandSammishasbeencompletedthrough2014.Inaddition,anEPAenforcementpolicydocument
contemplatesuptoanadditionalyeartoachievecompliance,throughApril2017,undercertaincircumstancesforreliabilitycritical
units.OnJune29,2015,theUnitedStatesSupremeCourtreversedaU.S.CourtofAppealsfortheD.C.Circuitdecisionthatupheld
MATS,rejectingEPA’sregulatoryapproachthatcostsarenotrelevanttothedecisionofwhetherornottoregulatepowerplant
emissionsunderSection112oftheCleanAirActandremandedthecasebacktotheU.S.CourtofAppealsfortheD.C.Circuitfor
furtherproceedings.TheU.S.CourtofAppealsfortheD.C.CircuitlaterremandedMATSbacktoEPA,whorepresentedtosuchcourt
thattheEPAisontracktoissueafinalizedMATSbyApril15,2016.Subjecttotheoutcomeofanyfurtherproceedingsbeforethe
U.S. Court ofAppeals for the D.C. Circuit and how the MATS are ultimately implemented, FirstEnergy's total capital cost for
compliance(overthe2012to2018timeperiod)iscurrentlyexpectedtobeapproximately$345million(CESsegmentof$168million
andRegulatedDistributionsegmentof$177million),ofwhich$202millionhasbeenspentthroughDecember31,2015($80million
atCESand$122millionatRegulatedDistribution).
AsaresultofMATS,EastlakeUnits13,AshtabulaUnit5andLakeShoreUnit18weredeactivatedinApril2015,whichcompletes
thedeactivationof5,429MWofcoalfiredplantssince2012.
OnAugust3,2015,FG,asubsidiaryofFES,submittedtotheAAAofficeinNewYork,N.Y.,ademandforarbitrationandstatementof
claimagainstBNSFandCSXseekingadeclarationthatMATSconstitutedaforcemajeurethatexcusesFG’sperformanceunderits
coaltransportationcontractwiththeseparties.Specifically,thedisputearisesfromacontractforthetransportationbyBNSFandCSX
ofaminimumof3.5milliontonsofcoalannuallythrough2025tocertaincoalfiredpowerplantsownedbyFGthatarelocatedin
Ohio.AsaresultofandincompliancewithMATS,thoseplantsweredeactivatedbyApril16,2015.InJanuary2012,FGnotified
BNSFandCSXthatMATSconstitutedaforcemajeureeventunderthecontractthatexcusedFG’sfurtherperformance.Separately,
onAugust4,2015,BNSFandCSXsubmittedtotheAAAofficeinWashington,D.C.,ademandforarbitrationandstatementofclaim
againstFGallegingthatFGbreachedthecontractandthatFG’sdeclarationofaforcemajeureunderthecontractisnotvalidand
seekingdamagesincluding,butnotlimitedto,lostprofitsunderthecontractthrough2025.Aspartofitsstatementofclaim,arightto
liquidateddamagesisalleged.Thearbitrationpanelhasdeterminedtoconsolidatetheclaimswithaliabilityhearingexpectedto
begininNovember2016,and,ifnecessary,adamageshearingisexpectedtobegininMay2017.Thedecisiononliabilityis
expectedtobeissuedwithinsixtydaysfromtheendoftheliabilityhearings.FirstEnergyandFEScontinuetobelievethatMATS
constitutesaforcemajeureeventunderthecontractasitrelatestothedeactivatedplantsandthatFG’sperformanceunderthe
contractisthereforeexcused.FirstEnergyandFES intendtovigorouslyasserttheirpositioninthearbitrationproceedings. If,
however,thearbitrationpanelrulesinfavorofBNSFandCSX,theresultsofoperationsandfinancialconditionofbothFirstEnergy
andFEScouldbemateriallyadverselyimpacted.FirstEnergyandFESareunabletoestimatethelossorrangeofloss.
FGisalsoapartytoanothercoaltransportationcontractcoveringthedeliveryof2.5milliontonsannuallythrough2025,aportionof
whichistobedeliveredtoanothercoalfiredplantownedbyFGthatwasdeactivatedasaresultofMATS.FGhasasserteda
defenseofforcemajeureinresponsetodeliveryshortfallstosuchplantunderthiscontractaswell.IfFirstEnergyandFESfailto
reacharesolutionwiththeapplicablecounterpartiestothecontract,andifitwereultimatelydeterminedthat,contrarytoFirstEnergy’s
andFES’belief,theforcemajeureprovisionsofthatcontractdonotexcusethedeliveryshortfallstothedeactivatedplant,theresults
ofoperationsandfinancialconditionofbothFirstEnergyandFEScouldbemateriallyadverselyimpacted.FirstEnergyandFESare
unabletoestimatethelossorrangeofloss.
Astobothcoaltransportationagreementsreferencedabove,FESpaidinsettlementapproximately$70millioninliquidateddamages
fordeliveryshortfallsin2014relatedtoitsdeactivatedplants.
Astoaspecificcoalsupplyagreement,FirstEnergyandAESupplyhaveassertedterminationrightseffectivein2015.Inresponseto
notificationofthetermination,thecoalsuppliercommencedlitigationallegingFirstEnergyandAESupplydonothavesufficient
justification to terminate the agreement. FirstEnergy andAE Supply have filed an answer denying any liability related to the
termination.Thismatteriscurrentlyinthediscoveryphaseoflitigationandnotrialdatehasbeenestablished.Thereare6milliontons
remainingunderthecontractfordelivery.Atthistime,FirstEnergycannotestimatethelossorrangeoflossregardingtheongoing
litigationwithrespecttothisagreement.
InSeptember2007,AEreceivedanNOVfromtheEPAallegingNSRandPSDviolationsundertheCAA,aswellasPennsylvania
andWestVirginiastatelawsatthecoalfiredHatfield'sFerryandArmstrongplantsinPennsylvaniaandthecoalfiredFortMartinand
WillowIslandplantsinWestVirginia.TheEPA'sNOVallegesequipmentreplacementsduringmaintenanceoutagestriggeredthepre
constructionpermittingrequirementsundertheNSRandPSDprograms.OnJune29,2012,January31,2013,andMarch27,2013,
EPA issued CAA section 114 requests for the Harrison coalfired plant seeking information and documentation relevant to its
operationandmaintenance,includingcapitalprojectsundertakensince2007.OnDecember12,2014,EPAissuedaCAAsection114
requestfor theFortMartincoalfiredplant seekinginformation anddocumentationrelevantto itsoperation andmaintenance,